| | | 請求(遲延利息)金額 ※計算式: 1.(甲)完工前已繳房地價款×利率 5/10,000 × 逾期日數1,213日 2.(乙)完工前已繳房地價款×利率 5/10,000 ×逾期日數697日 | |
| | | | 對被上訴人林宏達、華益建設有限公司請求金額暨具體計算公式(完工前已繳房地價款×利率5/10,000×逾期日數1,213日) |
| | | | 對被上訴人東亞建築經理股份有限公司、大陸工程股份有限公司請求金額暨具體計算公式(完工前已繳房地價款×利率5/10,000× 逾期日數697日) |
| | | | 9,652,000×5/10,000×1,213 =5,853,938 |
| | | | 9,652,000×5/10,000×697 =3,363,722 |
| | | | 15,180,000×5/10,000×1,213 =9,206,670 |
| | | | 15,180,000×5/10,000×697 =5,290,230 |
| | | | 15,380,000×5/10,000×1,213 =9,327,970 |
| | | | 15,380,000×5/10,000×697 =5,359,930 |
| | | | 15,870,000×5/10,000×1,213 =9,625,155 |
| | | | 15,870,000×5/10,000×697 =5,530,695 |
| | | | 15,748,000×5/10,000×1,213 =9,551,162 |
| | | | 15,748,000×5/10,000×697 =5,488,178 |
| | | | 13,530,000×5/10,000×1,213 =8,205,945 |
| | | | 13,530,000×5/10,000×697 =4,715,205 |
| | | | 16,118,000×5/10,000×1,213 =9,775,567 |
| | | | 16,118,000×5/10,000×697 =5,617,123 |
| | | | 17,990,000×5/10,000×1,213 =10,910,935 |
| | | | 17,990,000×5/10,000×697 =6,269,515 |
| | | | 10,440,000×5/10,000×1,213 =6,331,860 |
| | | | 10,440,000×5/10,000×697 =3,638,340 |
| | | | 10,880,000×5/10,000×1,213 =6,598,720 |
| | | | 10,880,000×5/10,000×697 =3,791,680 |
| | | | 11,230,000×5/10,000×1,213 =6,810,995 |
| | | | 11,230,000×5/10,000×697 =3,913,655 |
| | | | 11,366,000×5/10,000×1,213 =6,893,479 |
| | | | 11,366,000×5/10,000×697 =3,961,051 |
| | | | 8,790,000×5/10,000×1,213 =5,331,135 |
| | | | 8,790,000×5/10,000×1,213 =5,331,135 |
| | | | 11,350,000×5/10,000×1,213 =6,883,775 |
| | | | 11,350,000×5/10,000×697 =3,955,475 |
| | | | 8,710,000×5/10,000×1,213 =5,282,615 |
| | | | 8,710,000×5/10,000×697 =3,035,435 |
| | | | 12,240,000×5/10,000×1,213 =7,423,560 |
| | | | 12,240,000×5/10,000×697 =4,265,640 |
| | | | 12,940,000×5/10,000×1,213 =7,848,110 |
| | | | 12,940,000×5/10,000×697 =4,509,590 |
| | | | 12,800,000×5/10,000×1,213 =7,763,200 |
| | | | 12,800,000×5/10,000×697 =4,460,800 |